Project 13
Terra
- Nitrogen U.K. Ltd - Shutdown LCA Nitram and Nitric Acid Plants Mechanical
inspections, equipment overhaul and planned maintenance work carried out by International
Combustion Limited with first line supervision and labour resource provided by
ROCKALL. The
main jobs in the overhaul are:- Refractory
Repair HF Acid Wash of Evaporators and Pipework Tower Repairs Gas Cooler
Cleaning  Compressor
Overhauls Tails Gas Team Heater Repair Absorption Column Repack Shutdown
duration - 17 days ROCKALL
provided ICL with a second tier management and administration team comprising
of:-  COST
ENGINEER SAFETY ENGINEER MECHANICAL SUPERINTENDENTS (2) RIGGING SUPERINTENDENT
MATERIALS CONTROLLERS (2) TIMEKEEPER
In
the 72 hour period leading up to the start of the shut-down programme, ROCKALL
located and mobilised a quality, tried and tested labour force comprising:- RIGGERS
(16) MECHANICAL FITTERS (25) PIPE FITTERS (40) SAFETY STANDBY OPERATIVES
(12) LABOURERS (15) The
Shutdown Project was completed within budget and on time and with virtually no
labour turnover.
|