Project 9
Ocean
Technical Glass Construction
of a "fast track" £200 million glass manufacturing facility specialising in producing
glass for television screens and computer monitors on a green field site in Cardiff.
The scope of work involved supplying the Design and Build Contractor, Kajima
(UK) Engineering with a multi discipline team of Engineers and Supervisors to
oversee the activities of all Contractors on site from day one through to completion
and handover. Contract
duration - 6 months. Rockall
provided Kajima with permanent and contract engineering personnel when required
at short notice over the duration of the contract in the following job categories.

Civil Engineers Architects Architectural Engineers Planning Engineers
Quantity Surveyors Mechanical Engineers Electrical Engineers M
& E Supervisors
The
project was completed to schedule and within budget.
Rockall
were commended for the consistently high quality of Engineers supplied. |